The short answer for a compliance desk: BAAJA's binding constraints are calendars, not ideology — 180 days for agencies to rewrite NEPA procedures, 150 days for a challenger to file, and more than a year of state review before federal backstop siting applies. The Bipartisan American Affordability and Jobs Act is procedural machinery, and the projects that move first will be the ones that mapped those clocks before the rulemaking landed.
On Thursday, November 12, Congress was still debating the Senate Permitting Bill, formally the Bipartisan American Affordability and Jobs Act (S. 5653). Heatmap devoted a Shift Key episode to it, with Robinson Meyer, founding executive editor of Heatmap News, hosting, and the episode's own struggle to compress the package into an introduction is the tell. The recording is available on Apple Podcasts, Spotify, Amazon and YouTube. In brief, the bill would initiate a federal buildout of long-distance transmission, rework parts of the National Environmental Policy Act, change how the federal government works with tribes, rewrite parts of the Clean Water Act to generally give states less power, and rewrite the Endangered Species Act to generally give states more.
Three procedural statutes and one market rule, with most of the operational detail sitting in the NEPA title. The Congressional Research Service reads Division A, Title I of S. 5653 — introduced September 30 — as a rewrite with hard edges rather than discretionary guidance.
| Provision | What changes | Who has to act first |
|---|---|---|
| NEPA title | 180-day procedure rewrite; 150-day filing window; vacatur barred for NEPA-only claims | Agency counsel, permit applicants |
| FERC backstop | Siting authority for lines at or above 230 kV after more than a year of state review | Developers, state commissions |
| Planning | Regional and interregional planning codified | MISO, SPP and other RTOs; utilities |
| Cost allocation | Beneficiary-pays for qualifying lines | Transmission owners, consumer advocates |
| Large loads | 20 MW and above pays full incremental cost; states may create a separate rate class | Data centers, state commissions |
| Water, species, tribes | Clean Water Act narrower for states; Endangered Species Act wider for states; consultation timed to NEPA completion | Permittees, tribes, state agencies |
Because resource quality varies far more for wind than for solar, and the wire — not the turbine — converts that variance into revenue. Robinson Meyer borrowed his former co-host Jesse's framing on Shift Key: the spread between the worst and the best solar resource is about 2x, while the spread between the worst and the best wind resource is roughly 10x. Transmission can roughly double a solar project's economics; for wind it decides whether a project exists at all.
Pete Wyckoff adds the physics most spreadsheets miss. Wind scales to a power of three or four, so doubling the resource or the tower height produces a multiple, not a linear gain — which is why the same dollar of transmission does far more work in a high-wind corridor. MISO North, the Midwestern northern states, already leads the country on regional planning and still falls short, which makes it the best-case comparator rather than the finish line.
Wyckoff's Minnesota vantage point makes the seam concrete. The Dakotas and Western Minnesota straddle the MISO–SPP boundary — SPP being the Southwest Power Pool, whose territory includes a sliver of Western Minnesota and very little of the Southwest. Power clears at one price on one side and a different price on the other. Under Biden, the Minnesota Department of Commerce and six red states secured a bipartisan infrastructure law grant for seam lines; the grant survived a Trump-era cancellation review, and Wyckoff's point is that something so ordinary counting as remarkable shows how little has been built. Minnesota curtails wind even with a state-level 100 clean energy standard, because a standard does not add copper. Texas and ERCOT show the mirror-image failure: generation gets built at scale, and the interconnection queue is where the project dies.
It converts data center siting from an interconnection question into a cost-of-service evidentiary exercise. A facility at or above 20 MW must carry the full incremental cost of the generation, storage, transmission and distribution built on its behalf, and must keep covering those costs if it shuts early. States gain leverage they did not have: a dedicated rate class, charges above cost to serve, surplus revenue redirected to other customers' bills, and competitive open seasons that reward facilities offering the most.
Rhodium Group's assessment is that these ratepayer protections likely raise the cost of grid-connected power for the loads in question — a line item, not a rounding error. Its companion emissions finding is the other half of the story: the bill's worst-case climate outcome is roughly carbon neutral, with clean-energy gains and fossil-fuel effects largely offsetting. That is a national accounting result, and reading it as a project-level guarantee is one of the more common errors in circulation.
Because its theory of change is decarbonization speed rather than land protection, and it reads transmission as the binding constraint. That focus is structural: Evergreen was founded roughly five years ago by alumni of Jay Inslee's 2020 presidential campaign, which ran entirely on climate, and it works only on climate, decarbonization and clean energy — unlike older groups whose conservation and biodiversity mandates predate climate politics. The bill has divided the environmental community and the broader set of interest groups aligned with the Democratic Party.
| Groups opposing the bill | Groups supporting the bill |
|---|---|
| The Wilderness Society | AFL-CIO |
| Earth Justice | International Brotherhood of Electrical Workers |
| Al Gore | Electrician's Union |
| National Urban League | |
| Evergreen Action |
Lena Moffitt does not soften the tradeoffs. The bill is, in her words, "very much a compromise bill, with a lot of really hard tradeoffs in it that have genuinely kept me up in the middle of the night for months on end," and the endorsement rests on the judgement that "we are not going to be able to make that transition, simply put, without this transmission."
Who is speaking matters for how to read the endorsement. Moffitt is executive director, a New Mexico native with roughly a decade at the Sierra Club on Keystone XL and methane regulation, and earlier stints at the National Wildlife Federation's climate program and the Union of Concerned Scientists during the Waxman-Markey fight under Obama. Wyckoff is vice president of policy, an environmental scientist by training who moved from academia to Al Franken's office, then to Senator Tina Smith, then into Tim Walls' administration as Deputy Commissioner of Energy Resources at the Minnesota Department of Commerce, holding a regulatory seat at the Minnesota PUC and in both MISO and SPP.
The lineage is the Inflation Reduction Act. Both watched it pass at sunrise on Capitol Hill — bagel from the shop near the Heritage Foundation, per the Shift Key telling — and both argue BAAJA does not exist without the IRA, and that the White House and Senator Heinrich would not be as committed without that experience.
Treat enactment as the start of a documentation sprint, not the end of a lobbying campaign.
The Senate voted 73-25 to invoke cloture on the motion to proceed on the night of November 9, and by Thursday, November 12 the floor debate was still live. Democrats take larger majorities on Jan. 1, which is precisely the question Moffitt and Wyckoff keep fielding; their answer is that the package was negotiated among utilities, Republicans, Democrats and Trump, and that no better deal is coming around the corner.
For a compliance team the reading is unglamorous. Build the calendar on the bill as written, hold a second scenario for a narrower version, and do not assume the House takes up the Senate text unchanged.
No. Cloture on the motion to proceed passed 73-25, but a floor vote, amendments and House action remain, and the lame-duck calendar is short.
Federal backstop siting authority at FERC for qualifying interstate lines, available after more than one year of state review, plus a codified planning requirement that gives that authority something to attach to.
Because the arbitrage favors cheap wind and solar once the wire exists. Evergreen's bet is that removing the transmission constraint lets economics choose the resource mix — a bet Moffitt describes as accepting hard tradeoffs for a structural step.
Model the full incremental cost of service, assemble the cost-causation evidence, and engage the state commission on rate-class and open-season design while the details are still movable.
Mostly at the margins: the litigation clock and agency procedure changes touch pending and future authorizations, while the planning and cost-allocation provisions shape the next round of projects rather than the current queue.