The more than 70 senators who advanced the Bipartisan American Affordability and Jobs Act have built the strongest permitting coalition in years. The bill deserves to pass. It also needs a published agency review-capacity baseline, because the momentum will otherwise produce more litigation and more missed deadlines. The judgment would be wrong if the agencies that conduct environmental reviews already have enough full-time staff and contractor capacity to meet the new clocks, or if the deadlines are long enough that capacity is not the binding constraint. Neither condition is established in the text now moving through the Senate.
The Bipartisan American Affordability and Jobs Act, known as BAAJA, was introduced on September 30, 2026, by Senators Capito, Lee, Whitehouse and Heinrich. Senate leaders described it as the most significant permitting reform package Congress has considered in years, with new permitting deadlines, changes to judicial review and revisions to the National Environmental Policy Act, the Clean Water Act and the Endangered Species Act. More than 70 senators voted to advance it past a procedural hurdle. The manager's amendment released on Saturday revised transmission provisions and added benefits for power lines rebuilt with advanced technology.
The bill's central instrument is the statutory clock, which tells an agency to decide by a date. A clock does not hire reviewers, and it does not build the data systems that track a case from application to record of decision. The coalition has solved a political problem, but the administrative problem remains open.
The political achievement is not small. The bill would create a one-stop shop for large-scale power line approvals, putting transmission lines closer to the footing that natural gas pipelines already enjoy in federal review. It includes provisions to protect consumers from electricity price increases driven by data centers, according to FX678. The manager's amendment responded to concerns that concurrent federal and state permitting threatens states' authority. Each of these changes depends on agencies that can process the cases.
The stakes extend beyond Washington. At COP31 in Antalya, Turkey, governments are discussing the 35x35 pledge, which aims to electrify 35% of the world's final energy use by 2035. The world now uses electricity for 21% of end-use energy, and the Rhodium Group projects a likely rate of 28% by 2035. The gap between the pledge and the projection is partly a transmission gap. Transmission is what the permitting bill is supposed to deliver. If the bill sets deadlines that agencies cannot meet, the gap widens.
The baseline should have three elements. The first is full-time equivalents per agency, broken out by review function. A deadline is a promise made by people who do not control the workforce. An FTE baseline makes that workforce visible to Congress and the public before the first case arrives.
The second is a clear rule for fee-funded third-party contractors. Agencies can expand capacity without a new appropriation if they can charge applicants for third-party review, but the rules need to be clear on conflicts, quality control and transparency. Fee authority now varies by agency and by statute. Some agencies can charge applicants for third-party review; others cannot. Some can use the fees to hire contractors; others must return them to the Treasury. A uniform framework would let agencies hire contractors when a surge of applications arrives, and it would let Congress see whether the fees buy capacity. The Nature Conservancy's permitting reform white paper offers federal recommendations on permitting and project approval, and the Brookings Institution has argued for shorter timelines. A uniform fee framework would advance both goals.
The third is a defined backlog metric reported on the existing permitting dashboard. Without it, no one can tell whether the deadlines are moving cases or shifting them to the right. A backlog metric tells the public how many cases are pending, how long they have been pending and whether the trend is improving or worsening. If the deadlines are working, the backlog shrinks. If they are not, the backlog grows and the public knows. The metric should be defined clearly and audited independently. Without those safeguards, it becomes another number agencies can manipulate.
Congress has already built some of this machinery. As the environmental consulting firm ESASSOC noted in a recent analysis, Congress has established a permitting dashboard, a federal institution responsible for coordinating complex infrastructure reviews and a dedicated fund to improve federal permitting capacity. BAAJA creates parallel mechanisms without explaining how they will interact with the existing framework. That is where duplication and overlap become a capacity drain. Every new reporting requirement and every new coordination mechanism consumes staff time at the agencies the bill is trying to speed up. A published baseline would force the new deadlines to connect to the dashboard, the coordinating institution and the dedicated fund.
The strongest objection grants that capacity matters. It argues that the binding constraint is the substantive standard, not the headcount. NEPA asks agencies to analyze effects that courts can always find inadequately considered. Adding reviewers to a process that invites litigation simply produces more analysis to litigate over. On this view, the bill's changes to NEPA and judicial review matter more than any capacity baseline, and a baseline would become another compliance exercise. A related argument holds that the appropriations process is the right place to solve capacity, and that loading the authorizing bill with reporting requirements now would complicate a fragile coalition and delay a bill that already has more than 70 votes.
The objections deserve a direct answer. The substantive standard and the capacity to apply it are not substitutes. BAAJA changes the standard. If the agencies do not have the people to apply the new standard, the deadlines will fail. The Stanford Law School background paper published shortly before the bill's release chronicled substantial progress in recent years in improving environmental review, but it documents progress in process, not throughput. Process reform can reduce the time per case. It does not increase the number of cases an agency can handle at once. If deadlines compress the schedule without expanding capacity, the agency will either miss the deadline or shortcut the review. Both outcomes produce litigation, and litigation is the outcome the coalition can least afford.
The appropriations process is annual politics and cannot guarantee that resources arrive on the same schedule as the statutory deadlines. A capacity baseline appropriates no money. It requires agencies to count what they have and report what they face. That is the minimum condition for the deadlines to be credible.
Another objection holds that capacity metrics can be gamed. Agencies can reclassify staff or manipulate the backlog definition to make the numbers look better. That risk is real. It is a reason to design the metrics with clear definitions and independent reporting, not a reason to abandon them. A baseline with independent auditing is harder to game than a deadline with no baseline at all.
The bill should carry a published review-capacity baseline before the deadlines take effect. If the coalition will not accept that, it should at least delay the statutory deadlines until the baseline is published. Otherwise the bill is betting that agencies can do more with less. The House may take up the legislation in November, according to Guancha.cn. A baseline designed after passage would arrive too late. The vote count will not tell us whether the agencies holding the pen can hit the clocks Congress is about to set.