COP31's pro-nuclear momentum deserves conditional support, and the condition is disclosure: a standard project-readiness ledger covering enrichment contracts, fuel-supply origin, spent-fuel storage status and construction milestones. The technology case is credible; the delivery case is not yet auditable. This judgment would be wrong if fuel and waste constraints turn out to be trivially manageable, or if construction cost and capital, not transparency, are the only binding bottlenecks.
Reporting from the summit's opening day states that the 31st Conference of the Parties opened in Antalya, Turkey (GreencarbonWorld), the second year in a row that virtually every nation gathers while the United States stays away after its withdrawal from the 2015 Paris Agreement. The summit opened into extreme weather, with at least 11 southern Thai provinces under flood emergency and nearly 7-foot waves reported in the monsoon surge. The headline proposal is the 35x35 pledge, to electrify 35% of the world's final energy use by 2035. Today that share is 21%, and the Rhodium Group projects 28% by 2035. Civil society groups have pressed the summit to deliver, with one press release calling for COP31 to deliver climate action, end fossil fuel finance and advance clean electrification (For Our Climate). An international coalition has called for nuclear energy to be explicitly included in the implementation plans for the 35 by 35 target (NucNet). Coverage notes that governments are eyeing a second global stocktake as momentum builds for a fossil fuel transition (Carbon Pulse). An opinion piece on the summit argues that linking nuclear to the fossil fuel debate is the strongest available argument (West Asia Watch). The facts below are attributed to their sources; the judgments are mine.
The clearest sign that political momentum has outrun delivery is a procurement decision rather than a protest. Anthropic agreed to a $3.4 billion deal for 1.7 gigawatts of gas-fired engines (GreencarbonWorld). The report does not state the buyer's reasoning, but the scale of the contract suggests that near-term deliverability is doing the deciding. Data-center power demand is the growth story of the decade, and the fastest available firm capacity is winning the first tranches of it. The arithmetic is unforgiving: moving from 21% to 35% of final energy use in a decade requires a build rate of clean electricity that no recent historical period has matched, and the 28% projection implies a shortfall that gas, efficiency and demand shifts will otherwise fill.
On the policy side, the United States Senate is moving the Bipartisan American Affordability and Jobs Act, whose updated manager's amendment focuses on transmission lines, with a procedural vote scheduled for later today (GreencarbonWorld). The action is real, and it is about wires rather than reactors. The back end of the fuel cycle is also starting to be treated as a market question. A market research report published in September assessed the spent nuclear fuel sector using cumulative stored fuel, annual reactor discharges, wet-to-dry transfer activity and reprocessing throughput (Strategic Market Research). Investors are beginning to price the back end, which is another reason a common disclosure format would be useful.
Nuclear fuel looks like a commodity until the supply chain is examined. Reporting on United States regulatory hearings has described a fuel supply chain under strain, citing a Stanford Energy Center report from January that flagged tight uranium supply, geopolitical risk and rising costs (Toutiao). A commentary on the fuel supply chain states that only five plants worldwide carry out large-scale uranium conversion and that nearly half of global enrichment capacity is controlled by Russia (Feifan Shuo Energy on Toutiao). If that concentration figure holds, a supply disruption would be a systemic event rather than a line-item cost.
An analyst commenting on Xueqiu, Ed Coyne, argued that uranium accounts for less than 10% of a reactor's operating budget (Xueqiu). That is his view, not an industry statistic, but if it is broadly right, fuel is primarily a security-of-supply problem rather than a cost problem. Long-term contracts and diversified enrichment origins are the standard management tools, and a disclosure standard would make that management visible to lenders and host governments.
A securities filing on the nuclear fuel cycle, published in March, said the declaration to triple nuclear capacity by 2050 has been signed by 33 countries, and that demand is rising while supply investment has lagged, with geopolitical risk compounding the gap (Futunn). The filing also noted that the SMR market is maturing as energy-intensive companies seek nuclear for decarbonization, which means fuel demand could arrive in forms the current supply chain is not built to serve. The IAEA's 2026 Nuclear Technology Review adds a technical wrinkle: advanced fuel development is pushing the industry toward longer operating cycles, with some concepts aiming to stretch refueling intervals from 18 months to 24 months, and these advanced fuels need dedicated manufacturing facilities and new supply chains (2026 Nuclear Technology Review). A reactor without a qualified fuel design and a fabrication slot is a press release.
The back end is more visible. The IAEA review estimates that roughly 320,000 tonnes of heavy metal in spent fuel were in storage worldwide at the end of 2025, with many countries transferring material from wet pools to dry casks. Transfer is technically mature, yet slow and capital-intensive, and the cost of storage lands on ratepayers or taxpayers depending on the country's liability framework. Reprocessing and closed-cycle interest is rising, but the physical backlog remains. The same review counts 218 power reactors in 21 member states that have been shut down and await decommissioning, plus 23 units already fully decommissioned. The chemistry is often misunderstood. A discussion on r/NuclearPower noted that fuel rods are replaced because fission products accumulate and absorb neutrons; the uranium itself is not exhausted (r/NuclearPower). Spent fuel retains usable content, and the back-end question is whether that content will be recycled or stored. For project readiness, the operative question is simpler: where will the spent fuel go, and on what schedule?
Growth is happening where it can be scheduled. PSEG Power and Constellation Energy plan a 200 MW uprate at the Salem plant in New Jersey, tied to a Google supply agreement (Xueqiu). Uprates and life extensions are the near-term nuclear story, and they attract less opposition than new builds. That is why the disclosure debate should focus on new capacity, where fuel qualification and waste destination are genuinely unsettled.
The most serious objection to my thesis comes from nuclear supporters who say that adding disclosure requirements at this moment is self-defeating. Their case: the binding constraint on nuclear is construction cost, schedule and capital, not fuel or waste information. Uranium is a small share of operating cost; spent fuel sits safely in licensed dry casks; and the 35x35 target is already out of reach, with the Rhodium Group projecting 28% electrification against the 35% goal. In that light, a new reporting mandate adds process without adding megawatts, and it hands opponents a procedural tool to slow projects. Cost overruns at recent Western reactor builds are well documented, and a technology that arrives late contributes little to a 2035 target. Campaigners at the summit have described nuclear as too risky, too slow and too expensive to address the climate crisis, according to a post from The Cable NG (The Cable NG on Facebook). A disclosure rule could be used to validate that framing.
I take the objection seriously, and it is partly right. Disclosure alone builds nothing, and a badly designed mandate could become a litigation and licensing weapon. There is also a security risk: publishing facility-level enrichment contracts could expose dependencies that a dominant supplier could exploit. The objection assumes, however, that fuel and waste are already managed well enough that transparency adds no value. The concentration data suggest otherwise: five conversion plants, an enrichment sector with a dominant state supplier, a 320,000-tonne stockpile, and 218 reactors awaiting decommissioning are systemic facts that investors, insurers and host communities need to see. Construction risk is already disclosed in securities filings and lender due diligence; fuel origin and spent-fuel destination are the opaque parts of the pipeline. A well-designed standard can report aggregated supply data without exposing facility-level security details, which answers the weaponization and security concerns. The real question is whether the projects that survive scrutiny are the ones most likely to be financed.
COP31 cannot regulate the industry, but it can ask for a common readiness template, and the IAEA or national regulators could publish it. The template should be short enough that a project can complete it and investors can compare across jurisdictions.
| Disclosure item | What to report | Why it matters |
|---|---|---|
| Enrichment and conversion | Contract volumes, contract tenors, origin countries, swing capacity | Supply is concentrated; origin data reveals systemic risk |
| Fuel fabrication | Fuel design qualification, fabrication facility, first-core delivery date | Advanced fuels need new facilities; an unqualified design is not a project |
| Spent-fuel storage | Wet or dry storage, cask capacity, annual discharge projections, transfer schedule | 320,000 tonnes in storage; 218 reactors awaiting decommissioning |
| Disposal path | Repository commitment, interim storage licence, reprocessing contracts | Storage without an exit becomes a political liability |
| Construction milestones | EPC contract status, first concrete, fuel-load date, confidence level | The 35x35 target needs operable projects, not announcements |
Governments that want nuclear written into the 35x35 implementation plans should offer the template voluntarily and pre-empt the demand. Lenders and insurers should treat completed templates as a condition of finance, the way they already treat environmental impact statements, while industry associations publish aggregate supply and waste data annually so the systemic picture is visible without exposing individual facilities.
The pro-nuclear case at COP31 will not be won by another pledge. It will be won by projects that can show, before the first concrete is poured, where their fuel comes from and where their waste goes, with dates that hold up under scrutiny. A nuclear-friendly headline is cheap; a filled-in readiness template is not. A Chinese commentary on the summit put the point plainly: if delivery cannot keep up, even elegant text will not bring clean power to grids and households (Sohu). If the industry embraces that test, it will have a stronger claim on the 35x35 electrification push than any declaration signed in a resort city. If it resists, the momentum will remain political, and the gap between 35% and 28% will remain what it is today.